TR 2018 XR
Liquid dielectric transformers
Expedited Review Schedule (Revised)
| Date | Event |
|---|---|
| September 28, 2018 | Initiation of CBSA’s expedited review – IEN Hanchang Co., Ltd. (Hanchang) |
| October 15, 2018 | Importer’s response to CBSA’s Request for Information due |
| November 5, 2018 | Exporter’s response to CBSA’s Request for Information due |
| June 27, 2019 | Closing of the record |
| July 4, 2019, by noon | Case arguments due from all parties |
| July 11, 2019, by noon | Reply submissions due from all parties in respect of the case arguments |
| July 25, 2019 | Conclusion of CBSA’s expedited review |